Lets take a look at some detailed information regarding each of the electricity projects which will go live after the first phase or are still under consideration.

Suki Kinari Hydro Power Station
Capacity: 870 MW
Fuel: Water (Hydel)
Estimated Development Cost: $1.802 Billion
Location: River Kunhar Mansehra, KPK
Financing: Independent Power Producer (IPP) for 30 years
Estimated Commercial Operation: 2020
This is one of the biggest hydel projects under the CPEC. It is being developed and sponsored by M/s Mott McDonald UK and M/s Coney Blair of France, Al Jomaih Holding company, (LLC) Riyadh, Saudi Arabia and Eden Inc. Berhad, Malaysia.
The project will also bring Rs. 2 billion in profits per annum to KPK. Additionally, the project will be handed over to the KPK government 30 years from now without any charges.

The supplementary agreement has been approved and the land acquisition process is underway.


Karot Hydro Power Station
Capacity: 720 MW
Fuel: Water (Hydel)
Estimated Development Cost: $1.42 Billion
Location: River Jhelum, AJK and Punjab
Financing: Independent Power Producer (IPP)
Another one of the hydroelectric projects under the CPEC, it is being developed and sponsored by M/s SMEC (Australia) / China Three Gorges Corporation (CTGC), M/S Associated Technologies (Pvt) Ltd.
Estimated Commercial Operation: 2020
The project will be handed over to the Pakistani government after 30 years of operation. The land acquisition process is still underway but it is expected to be resolved very soon.


HUBCO Coal Power Plant
Capacity: 660 MW
Fuel: Coal (Imported)
Estimated Development Cost: $1.20 Billion
Location: Hub, Balochistan
Tariff: Rs 8.12 per KWh unit
Financing: Independent Power Producer (IPP)
Estimated Commercial Operation: 2018-2020
The project will be developed and sponsored by Hub-Power Company, a joint venture of China Power Hub Generation Company (Pvt) Ltd (CPHGC) is a joint venture between Hub Power Holdings Limited (HPHL). The IPP will make use of imported coal when it becomes operational. The project is being supervised by the Ministry of Water and Private Power and Infrastructure Board (PPIB).

Currently 30 Chinese personnel are working at the project site.

The power plant will be using Supercritical technology.


Kohala Hydel Project
Capacity: 1124 MW
Fuel: Water (Hydel)
Estimated Development Cost: $2.397 Billion
Location: Muzaffarabad, AJK
Tariff: Rs 8.12 per KWh unit
Financing: Independent Power Producer (IPP) for 30 years
This is the biggest hydel project under the CPEC. It is being developed and sponsored by the Chinese Company – Three Gorges.
Estimated Commercial Operation: 2024
The project will also bring Rs. 2.19 billion in profits per annum to AJK. Additionally, the project will be handed over to the AJK government 30 years from the date of launch without any charges.

The land acquisition process is underway.


Rahimyar Khan Coal Power Project
Capacity: 1320 MW
Fuel: Coal (Imported)
Estimated Development Cost: $1.60 Billion
Location: Rahimyar Khan, Punjab
Financing: Independent Power Producer (IPP)
Estimated Commercial Operation: Feasibility done. No estimate yet.
The project will be developed and sponsored by the Chinese Shanghai Electric Power Generation, China Machinery Engineering Corporation and Nishat Power Company.

The IPP will make use of imported coal when it becomes operational. The project will be supervised by the Ministry of Water and Punjab Power Development Board (PPDB).

The power plant is said to use Supercritical technology when it starts working.


Pakistan Wind Farm II
Capacity: 100 MW
Fuel: Wind
Estimated Development Cost: $150 Million
Location: Jhimpir, Sindh
Financing: Independent Power Producer (IPP)
Estimated Commercial Operation: No estimate
It is one of the few wind power projects being developed in Sindh. However, details are scarce regarding this project. If other projects are any indication, it won’t take long for this wind farm to go online.

The project will be executed under the supervision of Alternative Energy Development Board (AEDB).


Oracle Coalfields Mine Mouth Power Project
Capacity: 2×600 MW = 1200 MW
Fuel: Coal (Local)
Estimated Development Cost: Plant Cost to be declared later + $1.30 Billion Associated Cost
Location: Thar Block-VI, Sindh
Financing: Independent Power Producer (IPP)
Estimated Commercial Operation: 2022
Oracla Coalfields PLC UK is executing and financing this project. The independent power producer will make use of local coal from Thar Block-VI when it becomes operational. The Private Power and Infrastructure Board (PPIB) is supervising the project.

SSRL Thar Plant will use subcritical technology so unit prices will be slightly higher.

Associated with this plant is the $1.3 billion Thar Block-VI mining pit which will eventually fuel the plant. It will produce 4.0 metric ton of coal per annum initially, which will later increase to 8.0 metric tons per annum as per its growing requirements.


Muzaffargarh Coal Power Project
Capacity: 1320 MW
Fuel: Coal (Imported)
Estimated Development Cost: $1.60 Billion
Location: Muzaffargarh, Punjab
Financing: Independent Power Producer (IPP)
Estimated Commercial Operation: 2022 (rough estimate)
The project was to be financed under CPEC but has been delayed due to concerns over pollution.

The IPP will make use of imported coal when it becomes operational. The project will be supervised by the Ministry of Water and Punjab Power Development Board (PPDB).

The power plant is said to use Subcritical technology when it starts working.


Gwadar Coal /LNG / Oil Power Project
Capacity: 300 MW
Fuel: Coal (Imported), LNG, Oil
Estimated Development Cost: $600 Million
Location: Gwadar, Balochistan
Financing: To be decided
Estimated Commercial Operation: Still being planned.
The project is still being planned and a summary for an oil/LNG based power plant is under process. If and when operational, the power plant will make use of imported fuel only. The project will be supervised by the Gwadar Development Authority (GDA)



525MW Gas Power Plant
Capacity: 525 MW
Fuel: Gas
Estimated Development Cost: $550 Million
Location: Chichoki Malian, Punjab
There is still no information regarding the project aside from the specifications mentioned regarding the plant.
Estimated Commercial Operation: No estimate.
Note:

Supercritical technology means operating at very high pressures and temperatures resulting in higher efficiency.
Subcritical technology was normally used a few decades ago and has lesser efficiency than supercritical one. It operates at slightly lower temperature and pressure.
Once finished, Pakistan could be looking at an increased power generation capacity of close to 15,000 MW by 2023.

This concludes our coverage of electricity projects which were launched under CPEC and aim to resolve our loadshedding problems for good in the coming years. Let’s hope everything goes well and the electricity issue becomes a distant memory for all Pakistanis.

_________________
Startrack 2020 HD Spark
TCL 40" UHD 4K+3D Smart LED Tv
Shabbir 8ft A Quality Motorized
Covering 3.1E to 115E
Join My Youtube Channel
My Motorized Dish FULL HD


Top
 Profile Send private message  
 
 [ 1 post ] 

All times are UTC + 5 hours


Who Is Online

Users browsing this forum: No registered users and 0 guests


   Similar Topics   Author   Replies   Views   Last Post 
There are no new unread posts for this topic. Attachment(s) CPEC Related Road Projects Are Now Worth Over Rs. 1 Trillion

in TALK-SHAWK

FARRUKH

0

7

27 Dec 2016, 12:56 pm

FARRUKH View the latest post

There are no new unread posts for this topic. Pakistan In 2015 Without Electricity

in TALK-SHAWK

righme

0

22

18 Jun 2014, 1:25 pm

righme View the latest post

There are no new unread posts for this topic. Brilliant LED Projects: 20 Electronic Designs for .....

in E-BOOKS

ayanahmed

0

16

05 Jun 2015, 5:14 am

ayanahmed View the latest post

There are no new unread posts for this topic. Attachment(s) Rawalpindi Resident Sell Electricity to Grid & Save Thousand

in TALK-SHAWK

-=UMAIR=-

0

32

12 Aug 2016, 5:31 pm

-=UMAIR=- View the latest post

There are no new unread posts for this topic. New CPEC Loan to Upgrade Entire Rail Track

in TALK-SHAWK

-=UMAIR=-

0

8

01 Oct 2016, 8:42 pm

-=UMAIR=- View the latest post


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Valid XHTML 1.0 Transitional
News News Site map Site map SitemapIndex SitemapIndex RSS Feed RSS Feed Channel list Channel list
Powered by phpBB® Forum Software © phpBB Group

phpBB SEO